在线一本码道高清

Position : Home > Soft exam senior title > Soft exam senior title exam question bank > Soft exam senior title simulation test questions > 2020 soft exam information system project management division comprehensive knowledge simulation exercises (6)

Comprehensive knowledge simulation exercise for project management division of soft examination information system in 2020 (6)

点击量: Release time: January 9, 2020 09:01:21 Source: Global Online School Traffic:

Soft exam senior title registration, examination, check time, free SMS reminder

area

    Get VerifiedBook Now

    Please fill in the picture verification code to get the SMS verification code

    Can't see clearly, change a picture

    Get SMS Verification Code for Free

    [Abstract] To prepare for the test of the 2020 advanced soft exam information system project manager exam, the small editors of the Global Network School compiled the 2020 soft exam information system project manager's comprehensive knowledge simulation exercise. The little partners come to follow the editor Right. I hope everyone can take the exam smoothly. For more information about computer soft exams, please pay attention to the Global Professionals Soft Exam senior title channel.

    Comprehensive knowledge simulation exercise for 2020 soft exam information system project manager

    1. The preventive measures implemented are:

    A. Input for monitoring project work process

    B. Monitor the output of the project work process

    C. Output of overall change control

    D. Outputs that direct and manage project execution

    [Reference Answer] D

    2. The approved precautionary measures are:

    A. Input for monitoring project work process

    B. Monitor the output of the project work process

    C. Output of overall change control

    D. Outputs that direct and manage project execution

    [Reference Answer] C

    3. The following are configuration management activities during the overall change control process, except:

    A. Configuration identification

    B. Configuration status accounting

    C. Configuration verification and audit

    D. Configuration Change Control

    [Reference Answer] D

    4. Configuration verification and audit are:

    A. Verify that the performance and functional requirements identified in the configuration file have been met.

    B. Store and evaluate the configuration information needed to effectively manage products and information.

    C. Determine and verify product configuration.

    D. Review and approve changes requested.

    [Reference Answer] A

    5. In addition to being the output of the project closing, the administrative closing procedure is:

    A. Input for monitoring project work process

    B. Monitor the output of the project work process

    C. Input for overall change control

    D. Inputs to direct and manage project execution

    [Reference Answer] D

    6. The rejected change request is not only the output of the overall change control, but also the input of which process:

    A. Develop a project management plan

    B. Monitoring project work process

    C. Overall change control

    D. Direct and manage project implementation

    [Reference Answer] B

    7. The identified defect remedy is not only the output of the overall change control, but also the input of which process:

    A. Develop a project management plan

    B. Monitoring project work process

    C. Overall change control

    D. Direct and manage project implementation

    [Reference Answer] D

    8. The following statements about the strategic plan are correct, except:

    A. Results of the project charter

    B. Specify in the project statement of work

    C. All projects should support the strategic goals of the organization

    D. Considerations for project selection decisions

    [Reference Answer] A

    9. In addition to the project information system, which tool appears in all overall management processes:

    A. Expert judgment

    B. Project Management Methodology

    C. Career environmental factors

    D. Organizational process assets

    [Reference Answer] B

    10. The project team should confirm that the customer will accept the main results by:

    A. Customers are invited to express their opinions at the next working meeting.

    B. Obtain written documents.

    C. Ask the customer's staff for a full inspection.

    D. Document the positive and negative functions of the results.

    The above is the comprehensive knowledge simulation exercise of the 2020 soft examination information system project manager organized by Xiaobian. I hope it can help everyone. For more information about the soft exam, you can get a free SMS appointment reminder. ”免费下载学习。 At that time, the Global Network School will promptly remind you of the relevant information about the soft exam in 2019. Global Network Alumni Tips: In order to better prepare for the exam, Global Network School specially prepared computer soft exam review materials for you. If necessary, please click the " free download below the article" >>> Computer Soft Exam Questions / Exam Points "download and learn for free.

    share to: Edit: Jiao Xuewen

    Bind phone number

    In accordance with the requirements of the "People's Republic of China Cyber Security Law" to strengthen the real-name authentication mechanism, and at the same time to provide a more comprehensive experience of product services, please bind your mobile phone number.

    Appointment made

    This live broadcast is a live lesson for paid students

    Please make a reservation after purchasing the course

    直播、听课。 Global Online School Mobile Class App broadcast live and listen to lessons. Insta Future!

    Android version

    download

    iPhone version

    download
    Global Small Over-Global WeChat Official WeChat Service Platform

    Resolving problems APP download

    Free live one-click lessons

    Registration and other manual services

    Back to top