[Abstract] In order to help everyone prepare for the BIM exam, the editor of the Global Network School has compiled daily practice questions and answers for the daily practice of the BIM test. A little practice, a little harvest every day, a little growth every day, more exciting every day, and I wish everyone a smooth exam.

Multiple choice

1. [Single-choice question] For project management during the construction phase, the project manager department takes () as the core to manage the entire process of the construction project.

A. Project Technical Leader

B. Construction Project Manager

C. Supervision engineer

D. Corporate Legal Person

[Answer] B

[Analysis] The project management in the construction phase is the management of the entire process of the construction project by the project manager department with the construction project manager as the core.

2. [Single-choice question] BIM is a multi-dimensional model information integration technology developed on the basis of the original CAD technology in the past ten years, where multi-dimensional refers to three-dimensional space, four-dimensional time, five-dimensional (), N-dimensional and more Multi-application.

A. Design

B. Cost

C. Construction

D. Calculation

[Answer] B

[Analysis] BIM is a multi-dimensional model information integration technology developed on the basis of the original CAD technology in the past decade. Among them, multi-dimensional refers to three-dimensional space, four-dimensional time, five-dimensional cost, and N-dimensional more applications.

3. [Single-choice question] The () function based on BIM technology can greatly improve the performance of the technical target, and can well display the solution.

A. Informatization

B. Integration

C.3D

D. Synergy

[Answer] C

[Analysis] The 3D function based on BIM technology can greatly improve the performance of technical targets, and it can well realize the display of the solution.

4. [Single-choice question] The following are not the difficulties in the management of the current construction project ().

A. It is difficult to obtain data for each line of project management

B. Project engineering data is easy to save

C. Collision check of design drawings and construction difficulties

D. Project management coordination, sharing, and low cooperation efficiency

[Answer] B

[Analysis] The current difficulties and requirements of project management are:

(1) It is difficult to obtain data for each line of project management;

(2) The coordination, sharing and cooperation efficiency of all lines of project management are low;

(3) engineering data is difficult to save;

(4) It is more difficult to find the collision between design drawings and construction difficulties.

5. [Single-choice question] The following are not the advantages of using BIM technology for virtual construction guidance ().

A. Reflect construction difficulties in advance and avoid rework

B. Simulate the construction process and present the 3D model

C. Multi-version drawings for different teams

D. Simulate construction process and optimize construction process management

[Answer] C

[Analysis] Utilize the virtuality and visualization of BIM model to reflect construction difficulties in advance and avoid rework; simulate the construction process and present the 3D model to improve the efficiency of collaborative communication between departments; simulate the construction process and optimize the construction process management

"For the mountain man, it is based on a pile of soil, with thousands of feet; the well digger rises from a three-inch ridge, so as to be ten thousand feet deep." The above is the daily practice of the BIM exam brought to you by Global Network School. I hope everyone will persist in learning every day. ”领取自主学习资料。 For more details of the exams of the eight major members, please pay attention to the Global Online School. You can also click on the " Free Download " button below to get your self-learning materials.

share to: Edit: Gong Mingwei

Bind phone number

In accordance with the requirements of the "People's Republic of China Cyber Security Law" to strengthen the real-name authentication mechanism, and at the same time to provide a more comprehensive experience of product services, please bind your mobile phone number.

Appointment made

This live broadcast is a live lesson for paid students

Please make a reservation after purchasing the course

直播、听课。 Global Online School Mobile Class App broadcast live and listen to lessons. Insta Future!

Android version

download

iPhone version

download
Global Small Over-Global WeChat Official WeChat Service Platform

Resolving problems APP download

Free live one-click lessons

Registration and other manual services

Back to top